Progress is continuing on the public riverwalk near the River's Edge apartment
complex on Island Home Avenue - the riverwalk is about 75 percent
complete, according to the city
Backfilling operations are scheduled to begin next week, and structural
steel braces and beams have been put into place. Next, hollow core
planks will be installed.
In addition, crews have completed the curb and gutter tie-in at Splendid View Circle to Island Home Avenue.
The $2.5 million public infrastructure is on schedule to be finished this summer.